GAO: Weapons Costs Rose, Delivered Less
Source: Alalam TV, 01-04-2008
WASHINGTON--Government auditors issued a scathing review of dozens of the Pentagon's biggest weapons systems, saying ships, aircraft and satellites are billions of dollars over budget and years behind schedule.
The Government Accountability Office found that 95 major systems have exceeded their original budgets by a total of $295 billion, bringing their total cost to $1.6 trillion, and are delivered almost two years late on average.
In addition, none of the systems that the GAO looked at had met all of the standards for best management practices during their development stages.
Auditors said the Defense Department showed few signs of improvement since the GAO began issuing its annual assessments of selected weapons systems six years ago.
Michael Sullivan, director of the GAO's acquisition and sourcing team, said: "It's not getting any better by any means," and added, "It's taking longer and costing more."
The Pentagon has doubled the amount it has committed to new systems, from $790 billion in 2000 to $1.6 trillion last year, according to the 205-page GAO report.
Total acquisition costs in 2007 for major defense programs increased 26 percent from first estimates. In 2000, 75 programs had cost increases totaling 6 percent.
Development costs in 2007 for the systems rose 40 percent from initial projections, compared with 27 percent in 2000.
The government is facing higher development costs on eight major programs, including Lockheed Martin's Joint Strike Fighter and Boeing's Future Combat Systems, a technology to connect unmanned aircraft and vehicles.
The prices for those two programs have risen 36 percent and 40 percent, respectively, from the initial contracts, the GAO said.
The GAO's Sullivan said the reasons for the cost overruns and delays are threefold: There are too many programs chasing too few dollars; technologies are often not mature enough to go into production; and it takes too long to design, develop and produce a system.
Steven L. Schooner, co-director of the government procurement law program at George Washington University, said the GAO's report reveals the recurring problems the Pentagon faces with its costly procurements.
"The nature of major weapon systems development is that you have to expect that the initial estimates, and typically the initial contracts, are overly optimistic and unrealistic," he said.
WASHINGTON--Government auditors issued a scathing review of dozens of the Pentagon's biggest weapons systems, saying ships, aircraft and satellites are billions of dollars over budget and years behind schedule.
The Government Accountability Office found that 95 major systems have exceeded their original budgets by a total of $295 billion, bringing their total cost to $1.6 trillion, and are delivered almost two years late on average.
In addition, none of the systems that the GAO looked at had met all of the standards for best management practices during their development stages.
Auditors said the Defense Department showed few signs of improvement since the GAO began issuing its annual assessments of selected weapons systems six years ago.
Michael Sullivan, director of the GAO's acquisition and sourcing team, said: "It's not getting any better by any means," and added, "It's taking longer and costing more."
The Pentagon has doubled the amount it has committed to new systems, from $790 billion in 2000 to $1.6 trillion last year, according to the 205-page GAO report.
Total acquisition costs in 2007 for major defense programs increased 26 percent from first estimates. In 2000, 75 programs had cost increases totaling 6 percent.
Development costs in 2007 for the systems rose 40 percent from initial projections, compared with 27 percent in 2000.
The government is facing higher development costs on eight major programs, including Lockheed Martin's Joint Strike Fighter and Boeing's Future Combat Systems, a technology to connect unmanned aircraft and vehicles.
The prices for those two programs have risen 36 percent and 40 percent, respectively, from the initial contracts, the GAO said.
The GAO's Sullivan said the reasons for the cost overruns and delays are threefold: There are too many programs chasing too few dollars; technologies are often not mature enough to go into production; and it takes too long to design, develop and produce a system.
Steven L. Schooner, co-director of the government procurement law program at George Washington University, said the GAO's report reveals the recurring problems the Pentagon faces with its costly procurements.
"The nature of major weapon systems development is that you have to expect that the initial estimates, and typically the initial contracts, are overly optimistic and unrealistic," he said.